Home›News›Seajacks Announces Zaratan Construction Summary (UK)
News

August 17, 2011 · about 15 years ago

Seajacks Announces Zaratan Construction Summary (UK)

In February 2010 Seajacks entered into a contract with GustoMSC to provide the Basic Design Package for two purpose built wind farm installation vessels. In June 2010 Seajacks entered into a contract with Lamprell shipyard to build these new vessels and Seajacks will take delivery of the first new-b

1 minutes read
  • LinkedIn
  • X
  • Email

In February 2010 Seajacks entered into a contract with GustoMSC to provide the Basic Design Package for two purpose built wind farm installation vessels.

In June 2010 Seajacks entered into a contract with Lamprell shipyard to build these new vessels and Seajacks will take delivery of the first new-build, Seajacks Zaratan, in May 2012, and the additional new-build shortly thereafter.

These self-propelled jack-ups have been designed specifically to service the wind farm installation market in the harsh operating environment of the North Sea, as well as to provide services to the oil and gas industry. The vessels will be a modified version of the MSC NG5500 design, which incorporates a fully redundant DP2 propulsion system, accommodations for 90 persons, and an 800T leg encircling crane designed by MSC.

Seajacks Zaratan Construction Summary – 11/08/2011

STRUCTURAL

Hull:

Spud Cans:

Legs:

Main Deck:

Accommodation:

Foundations:

Cable Trays:

Electric Cable:

Commenced running 690V cable on 2/8/11

Machinery Installation:

The following have been installed:-

Main equipment received on site and stored: –

Pipe work:

800T Crane:

Auxiliary Cranes:

Jacking System:

Vessel still on schedule for May 2012 delivery

[mappress]

Source: seajacks, August 17, 2011

Reach the offshoreWIND.biz industry in one go!

offshoreWIND.biz is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow offshoreWIND.biz on:

Filed under

News

Daily offshore wind news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Cadeler Adds Wind Ace to Fleet, First Stop East Anglia Two
  2. 2Turbine Installation at Thor Offshore Wind Farm Reaches Halfway Point
  3. 3South Korean Cable Maker Takes Delivery of Its Second Cable Laying Vessel
  4. 4Aker Solutions Joins Bellrock Floating Offshore Wind Farm Team

Daily offshore wind news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free