offshoreWIND.biz
  • Fixed-Bottom
  • Floating Wind
  • Supply Chain
  • News
  • About
  • Contact
JobsNewsletter
offshoreWIND.biz logo
Topics
  • Fixed-Bottom
  • Floating Wind
  • Supply Chain
  • Power-to-X
  • Grid Connection
Network
  • Dredging Today
  • NavalToday
  • Offshore Energy
  • Offshore Wind
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Privacy
  • Report your news

© 2026 Navingo. All rights reserved.

Home›News›Carnegie Completes Preliminary Design for CETO (Australia)
News

December 8, 2011 · about 14 years ago

Carnegie Completes Preliminary Design for CETO (Australia)

Wave energy developer Carnegie Wave Energy Limited announced the completion of the preliminary design for the first CETO grid-connected project. Following the successful in-ocean trial of the CETO 3 commercial scale unit earlier this year, Carnegie’s technical team has analysed a huge quantity of da

3 minutes read
  • LinkedIn
  • X
  • Email

Wave energy developer Carnegie Wave Energy Limited announced the completion of the preliminary design for the first CETO grid-connected project.

Following the successful in-ocean trial of the CETO 3 commercial scale unit earlier this year, Carnegie’s technical team has analysed a huge quantity of data allowing further validation and development of the CETO design utilising Carnegie’s virtual modelling capabilities. This analysis and design work has focused on the full CETO system including the CETO unit design and foundations, pipeline and onshore power generation facility.

It concludes that the first grid-connected CETO demonstration project should be between 1 and 5MW peak capacity with an optimum of approximately 2MW peak.

Carnegie’s CEO and Managing Director, Dr Michael Ottaviano said,

“The completion of the preliminary design for the 2MW grid-connected project represents a major step forward in CETO’s technology maturity. The next phase of the process is for Carnegie to confirm a final location for this demonstration project. This will be Carnegie’s first power project and will deliver our first project-based revenues through the sale of the electricity generated.”

Selection of the location of the project site will allow the completion of detailed project design ahead of project construction.

Unit Optimisation

The CETO 3 analysis has provided the basis to optimise the Buoyant Actuator’s hydrodynamic properties to increase power output through more efficient energy capture and conversion.

Through optimisation of the Buoyant Actuator geometry, the preliminary design offers a two-fold increase in power production from the CETO 3 unit, with only relatively minor modifications, thereby delivering a significant reduction in the cost of generation.

Power Generation Facility

The onshore power generation facility contains the hydro-electric equipment including the Pelton Wheel Turbine, electrical switchgear and the instrumentation and control system. The preliminary design ensures high availability through redundant systems, in particular the turbine and generator.

Significant effort has been put toward designing, modelling and simulating the control algorithm that regulates the pressures in the pipelines. The physical footprint of the onshore facility has also been minimised to allow flexibility in siting and to ensure minimal visual impact.

Foundation

The design of the pile foundation has been largely focussed on the integration of a quick-connect system to allow CETO units to be installed and operational within a 24 hour window. This is in contrast to the 7 days required for the CETO 3 installation. The design incorporates both the structural and hydraulic connections using proven technology originating from offshore oil and gas applications. The new installation method, devised following learnings from the CETO 3 deployment, also tailors the diving and vessel requirements to those that are locally available in all prospective demonstration sites reducing installation cost and risk.

Pipeline to Shore

A small bore (200mm nominal diameter) pipeline carries the hydraulic energy back to shore from the CETO unit array and has been a focus of hydraulic modelling and optimisation work. Transient effects have been managed through careful sizing of surge vessels allowing a smaller pipeline than would have otherwise been possible. At the outlet of the turbine a similar pipeline returns the water-based working fluid back to the array for re-pressurisation. Optic fibre communications cables piggy-back the pipeline connecting the CETO unit instrumentation to the control system onshore.

[mappress]

Offshore WIND staff, December 08, 2011; Image: carnegiewave

Reach the offshoreWIND.biz industry in one go!

offshoreWIND.biz is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow offshoreWIND.biz on:

Filed under

News

Daily offshore wind news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Cadeler Adds Wind Ace to Fleet, First Stop East Anglia Two
  2. 2Turbine Installation at Thor Offshore Wind Farm Reaches Halfway Point
  3. 3South Korean Cable Maker Takes Delivery of Its Second Cable Laying Vessel
  4. 4Aker Solutions Joins Bellrock Floating Offshore Wind Farm Team

Daily offshore wind news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free