In spring of 2012 , Jumbo’s DP2 heavy lift vessel Jumbo Javelin successfully installed the first Transition Pieces (TPs) for the Anholt Offshore Wind Farm. By the end of the summer , all TPs have been installed on 111 monopiles.
Jumbo Javelin installed the TP’s with a record-breaking installation rate of 3 TP’s per day. The transport, installation, access to the TP’s and grouting was done without any Lost Time Injuries (LTI=0).
The following is a video of the installation of TPs at Abholt Offshore Wind Farm:
[mappress]
Offshore WIND Staff, February 14, 2013; Image: jumboshipping