The cabling work at the Butendiek offshore wind farm is half done, VSMC informed via social media.
The company said that 6 strings and 42 cables with a total length of 40km have been installed at the offshore wind farm site in the German Bight some 34 km west of the island Sylt.
A total of 86 individual cables will be installed between the turbines, including 6 redundancy cables, giving a total length of infield cabling of approximately 90 km. Termination, testing and commissioning of the 12 cable strings will be performed using in-house resources.