Dong awarded CMP a contract to construct & install a complete berthing system for the crew transfer vessels in Barrow in Furness.
It included dredging, socketing piles into rock and construction of heavy concrete pontoons on site and the fabrication and installation of steel access platform and bridge.
The pontoon facility was regularly tested close to its maximum design conditions on a number of occasions between December 2013 and February 2014.