Home›Grid Connection›Dudgeon Halfway Done
Grid Connection

June 3, 2016 · about 10 years ago

Dudgeon Halfway Done

Installation works on the 402MW Dudgeon offshore wind farm are progressing according to plan and the project is halfway to being completed, according to Dudgeon Offshore Windfarm Limited (DOWL). The wind farm’s export cables were laid and the jacket for the offshore substation was installed in May.

2 minutes read
  • LinkedIn
  • X
  • Email

Installation works on the 402MW Dudgeon offshore wind farm are progressing according to plan and the project is halfway to being completed, according to Dudgeon Offshore Windfarm Limited (DOWL).

The wind farm’s export cables were laid and the jacket for the offshore substation was installed in May. The crane vessel Oleg Strashnov has installed half of the 67 foundations at the site, according to DOWL.

The first foundations at the site were installed in early April.

“The project is really starting to become visible and the Dudgeon Bank is no longer an untouched area,” said Dudgeon project director Olav-Bernt Haga.

The Dudgeon project celebrated Norway’s Constitution Day by installing the substation jacket on the field on 17 May. Built by SLP in Lowestoft the jacket was installed by the Stanislav Yudin vessel.

The topside, which constitutes the substation, was constructed by the same yard and will be ready for installation in August. This operation will be performed by Oleg Strashnov, the same vessel which is currently installing the foundations – the huge monopiles and the transition pieces – for the towers and turbines that will arrive later.

”We have had good progress. They are installing an average of three foundations per week, but in this area we are of course at the mercy of the weather,“ said Svein Aage Gurrik, who is in charge of the Dudgeon project’s marine operations.

The second and last export cable reached the jacket in May after having been pulled from the landfall in Weybourne.

Cables between the wind turbines and the substation are now to be laid. Electricity will be transmitted through export cables from the substation to the Weybourne landfall, and then by onshore underground cables to Necton where it will be transformed once more before it enters the National Grid.

The onshore activity is also high: the Necton substation is almost completed, and cable-laying from Weybourne to Necton is about to be finished.

Great Yarmouth is hiring operations personnel and September sees the opening of a new office building and base, together with a naming ceremony for the service vessel from Esvagt to be used in the Dudgeon operating phase.

”We have many ongoing activities at the moment, and fortunately most of them are proceeding as planned. The project has not had any serious injuries,“ said Haga.

The Dudgeon offshore wind farm, owned by Statoil, Statkraft and Masdar, will comprise 67 Siemens 6MW turbines, and is expected to be commissioned by early 2017.

Statoil is in charge of the Dudgeon offshore wind farm in the development, commissioning and O&M phases. Co-owners in the project are Statkraft and Masdar. The total investment in the offshore wind farm, which was officially approved in 2014, is estimated at GBP 1.5 billion.

Reach the offshoreWIND.biz industry in one go!

offshoreWIND.biz is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow offshoreWIND.biz on:

Filed under

Grid ConnectionVesselsWind Farm Update

Daily offshore wind news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Cadeler Adds Wind Ace to Fleet, First Stop East Anglia Two
  2. 2Turbine Installation at Thor Offshore Wind Farm Reaches Halfway Point
  3. 3South Korean Cable Maker Takes Delivery of Its Second Cable Laying Vessel
  4. 4Aker Solutions Joins Bellrock Floating Offshore Wind Farm Team

Related articles

Aker Solutions Joins Bellrock Floating Offshore Wind Farm Team
Floating Wind

Aker Solutions Joins Bellrock Floating Offshore Wind Farm Team

12 days ago

Daily offshore wind news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free

Related news

Aker Solutions Joins Bellrock Floating Offshore Wind Farm Team
Floating Wind

Aker Solutions Joins Bellrock Floating Offshore Wind Farm Team

12 days ago