offshoreWIND.biz
  • Fixed-Bottom
  • Floating Wind
  • Supply Chain
  • News
  • About
  • Contact
JobsNewsletter
offshoreWIND.biz logo
Topics
  • Fixed-Bottom
  • Floating Wind
  • Supply Chain
  • Power-to-X
  • Grid Connection
Network
  • Dredging Today
  • NavalToday
  • Offshore Energy
  • Offshore Wind
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Privacy
  • Report your news

© 2026 Navingo. All rights reserved.

Home›Grid Connection›Siemens and MPI Adventure Install All Sandbank Turbines
Grid Connection

January 23, 2017 · about 9 years ago

Siemens and MPI Adventure Install All Sandbank Turbines

The installation vessel MPI Adventure and Siemens have installed all 72 turbines at the 288MW Sandbank offshore wind farm three months sooner than initially planned. The final Siemens SWT-4.0 130 turbine was installed on Saturday, 21 January, Vattenfall, the majority owner and developer of the wind

3 minutes read
  • LinkedIn
  • X
  • Email

The installation vessel MPI Adventure and Siemens have installed all 72 turbines at the 288MW Sandbank offshore wind farm three months sooner than initially planned.

The final Siemens SWT-4.0 130 turbine was installed on Saturday, 21 January, Vattenfall, the majority owner and developer of the wind farm, said.

The first Sandbank wind turbine was installed at the end of July 2016.

Currently 65 of all 72 wind turbines are delivering electricity to the German electricity grid.

Once the Sandbank wind farm is in full operation, an offshore substation will collect the wind energy of all 72 turbines, transform it from an AC voltage of 33 kilovolts (kV) to 155 kV, and deliver it to a converter station, from where the energy will be transported as DC over a distance of 165 kilometres to the landing point in Büsum, Schleswig-Holstein.

Various factors have accelerated the installation of the Sandbank wind turbines, according to Vattenfall. The installation vessel performed well with the effect that, under good weather conditions, the team was able to install one wind turbine per day.

During the commissioning phase of the wind turbines, a modified type of vessel equipped with a walk-to-work gangway was deployed by the project for the first time in the German North Sea. This system equalizes the wave motions of the North Sea and features a special gangway that enables the commissioning teams to step over to the wind turbines directly, with sea conditions of up to 2.5 metres in height. The new concept also enables for work with enhanced safety standards and to be carried out 24 hours per day, Vattenfall said.

“We are very pleased that the installation of the wind turbines for Sandbank was running so successfully,” said Martin Zappe, technical Head of the project at Vattenfall.

“The technology deployed on the project as well as the co-operation between all involved parties have gained a lot in terms of maturity. Projects of this size are now much more standardized and efficient. We will use these experiences for future projects to implement them as cost efficient as possible, also with regards to the new auction system for coming offshore projects in Germany.”

Vattenfall holds a 51% stake in Sandbank Offshore GmbH, which was set up to implement the project, while Stadwerke München (SWM) holds a 49% stake.

Sandbank is the second joint offshore wind project for Vattenfall and SWM. Together with the fully commissioned sister-project DanTysk, the wind farms provide a combined portfolio of 576 MW of installed generation capacity.

Christian Vogt, Head of Corporate Investment Management at Stadtwerke München, said: “Offshore wind power plays a key role to meet SWM’s ambitious targets for the expansion of renewable energy. By 2025, SWM is aiming to produce as much green electricity as required to power the entire city of Munich. Sandbank is SWM’s fourth offshore project, which is implemented successfully and even faster than originally scheduled. I would like to thank all those who contribute with their commitment to the success of this very complex project.”

Reach the offshoreWIND.biz industry in one go!

offshoreWIND.biz is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow offshoreWIND.biz on:

Filed under

Grid ConnectionVesselsWind Farm Update

Daily offshore wind news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Cadeler Adds Wind Ace to Fleet, First Stop East Anglia Two
  2. 2Turbine Installation at Thor Offshore Wind Farm Reaches Halfway Point
  3. 3South Korean Cable Maker Takes Delivery of Its Second Cable Laying Vessel
  4. 4Aker Solutions Joins Bellrock Floating Offshore Wind Farm Team

Related articles

Aker Solutions Joins Bellrock Floating Offshore Wind Farm Team
Floating Wind

Aker Solutions Joins Bellrock Floating Offshore Wind Farm Team

14 days ago

Daily offshore wind news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free

Related news

Aker Solutions Joins Bellrock Floating Offshore Wind Farm Team
Floating Wind

Aker Solutions Joins Bellrock Floating Offshore Wind Farm Team

14 days ago