Home›Wind Farm Update›DONG Tables Hornsea Project One Offshore Construction Schedule
Wind Farm Update

August 24, 2017 · about 9 years ago

DONG Tables Hornsea Project One Offshore Construction Schedule

DONG Energy is currently undertaking the necessary preparations to begin offshore works on the 1.2GW Hornsea Project One offshore wind farm which are scheduled to start in September.

1 minutes read
  • LinkedIn
  • X
  • Email

DONG Energy is currently undertaking the necessary preparations to begin offshore works on the 1.2GW Hornsea Project One offshore wind farm which are scheduled to start in September.

Pre-installation works include activities such as boulder clearance and the inspection of potential unexploded ordnance (UXO) items.

As of July, 21 confirmed UXO targets are currently planned for removal, DONG said.

Following the completion of the boulder and UXO removal activities, DONG will start preliminary offshore export cable installation works in September.

Scour protection works are planned to start in the fourth quarter of 2017 and are expected to be completed in the fourth quarter of 2018.

Installation of the four offshore substations is scheduled to commence in the second quarter of 2018.

All other offshore works, such as the installation of foundations and inter-array cables, are currently scheduled to commence in early 2018, DONG said.

Once operational in 2020, Hornsea Project One will become the largest offshore wind farm in the world, consisting of up to 174 turbines. The Siemens 7MW turbines will be located 120km off the Yorkshire coast, covering an area of approximately 407km2.

Reach the offshoreWIND.biz industry in one go!

offshoreWIND.biz is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow offshoreWIND.biz on:

Filed under

Wind Farm Update

Daily offshore wind news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Cadeler Adds Wind Ace to Fleet, First Stop East Anglia Two
  2. 2Turbine Installation at Thor Offshore Wind Farm Reaches Halfway Point
  3. 3South Korean Cable Maker Takes Delivery of Its Second Cable Laying Vessel
  4. 4Aker Solutions Joins Bellrock Floating Offshore Wind Farm Team

Related articles

Principle Power Wins O&M Contract for EFGL Floating Foundations
Operations & Maintenance

Principle Power Wins O&M Contract for EFGL Floating Foundations

20 days ago

Clarksons Wins Port & Agency Services Contract for OranjeWind Offshore Wind Farm
Ports & Logistics

Clarksons Wins Port & Agency Services Contract for OranjeWind Offshore Wind Farm

21 days ago

Daily offshore wind news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free

Related news

Principle Power Wins O&M Contract for EFGL Floating Foundations
Operations & Maintenance

Principle Power Wins O&M Contract for EFGL Floating Foundations

20 days ago
Clarksons Wins Port & Agency Services Contract for OranjeWind Offshore Wind Farm
Ports & Logistics

Clarksons Wins Port & Agency Services Contract for OranjeWind Offshore Wind Farm

21 days ago