Home›Grid Connection›Moray East Offshore Construction Ramps Up
Grid Connection

October 2, 2020 · about 5 years ago

Moray East Offshore Construction Ramps Up

Cable laying vessel Living Stone has started the first inter-array cable installation campaign at the 950 MW Moray East wind farm offshore Scotland. The wind farm will feature 100 66 kV inter-array cables and two offshore substation interconnector cables supplied by JDR Cable System. The installatio

2 minutes read
  • LinkedIn
  • X
  • Email
Moray East Offshore Construction Ramps Up

Cable laying vessel Living Stone has started the first inter-array cable installation campaign at the 950 MW Moray East wind farm offshore Scotland.

The wind farm will feature 100 66 kV inter-array cables and two offshore substation interconnector cables supplied by JDR Cable System.

The installation campaign will be carried out in three phases. The first campaign started on 29 September and will continue for eight weeks.

Boskalis is in charge of supplying and installing the inter-array cables for the 100-turbine project.

Export Cables

Cable laying vessel NKT Victoria is expected to lay the wind farm’s three export cables by 3 October. Havila Phoenix is burying the cables.

The first export cable made landfall at Inverboyndie in late August.

Cable burial and trenching work is ongoing, with the trenching expected to continue until early November.

This will be followed by a separate campaign to install remedial protection over the cables on any remaining unburied or unprotected sections.

NKT is in charge of delivering and installing the wind farm’s export cables.

Foundations

As of 28 September, 35 out of the 100 turbine jacket foundations were installed at the site some 22 kilometres off the Aberdeenshire coast by Seajacks Scylla.

The wind farm’s three Offshore Transformer Modules (OTMs) have been in place since mid-September.

DEME is the EPCI contractor for the wind farm’s turbine foundations and three offshore substation foundations, as well as for the transport and installation of the OTMs.

Moray East will feature 100 MHI Vestas 9.5 MW wind turbines scheduled for full commissioning in 2022.

Moray Offshore Windfarm East Ltd (MOWEL), the developer of the project, is a joint venture company owned by Diamond Green Limited (33.4%), Ocean Winds (56.6%) and CTG (10%).

Reach the offshoreWIND.biz industry in one go!

offshoreWIND.biz is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow offshoreWIND.biz on:

Filed under

Grid ConnectionWind Farm Update

Daily offshore wind news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Cadeler Adds Wind Ace to Fleet, First Stop East Anglia Two
  2. 2Turbine Installation at Thor Offshore Wind Farm Reaches Halfway Point
  3. 3South Korean Cable Maker Takes Delivery of Its Second Cable Laying Vessel
  4. 4Aker Solutions Joins Bellrock Floating Offshore Wind Farm Team

Daily offshore wind news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free