offshoreWIND.biz
  • Fixed-Bottom
  • Floating Wind
  • Supply Chain
  • News
  • About
  • Contact
JobsNewsletter
offshoreWIND.biz logo
Topics
  • Fixed-Bottom
  • Floating Wind
  • Supply Chain
  • Power-to-X
  • Grid Connection
Network
  • Dredging Today
  • NavalToday
  • Offshore Energy
  • Offshore Wind
  • Maritieme Vacaturebank
Company
  • Advertising
  • Newsletter
  • Jobs
  • Privacy
  • Report your news

© 2026 Navingo. All rights reserved.

Home›Wind Farm Update›Moray East Wind Turbine Installation Hits Quarter Mark
Wind Farm Update

April 20, 2021 · about 5 years ago

Moray East Wind Turbine Installation Hits Quarter Mark

The Bold Tern jack-up vessel has installed 24 wind turbines at the Moray East offshore wind farm in Scotland. The 100-turbine project is now one installation away from reaching a quarter of its wind turbines in place. The 24th Vestas (MHI Vestas) 9.5 MW unit was installed on 17 April, according to M

1 minutes read
  • LinkedIn
  • X
  • Email
First wind turbine being installed at Moray East offshore wind farm

The Bold Tern jack-up vessel has installed 24 wind turbines at the Moray East offshore wind farm in Scotland.

The 100-turbine project is now one installation away from reaching a quarter of its wind turbines in place.

The 24th Vestas (MHI Vestas) 9.5 MW unit was installed on 17 April, according to Moray East’s latest Notice of Operations, after the work started in mid-January . Bold Tern is picking up the components at the Port of Nigg, where Global Energy Group’s facility is serving as the onshore pre-assembly site for the project, carrying a batch of four wind turbines to the Moray East site at a time.

The commissioning work is being performed from Acta Centaurus and supported by two crew transfer vessels, HST Harri and Windcat 40 .

All three of Moray East’s offshore transformer modules (OTMs) have been in place since September 2020 and inter-array cable laying has been completed recently, with burial, termination and testing works still ongoing.

The 950 MW offshore wind farm, scheduled for commissioning in 2022, is being developed by Moray Offshore Windfarm East Ltd (MOWEL), a joint venture company owned by Ocean Winds (56.6%) Diamond Green Limited (33.4%), and CTG (10%).

Reach the offshoreWIND.biz industry in one go!

offshoreWIND.biz is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow offshoreWIND.biz on:

Filed under

Wind Farm Update

Daily offshore wind news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Cadeler Adds Wind Ace to Fleet, First Stop East Anglia Two
  2. 2Turbine Installation at Thor Offshore Wind Farm Reaches Halfway Point
  3. 3South Korean Cable Maker Takes Delivery of Its Second Cable Laying Vessel
  4. 4Aker Solutions Joins Bellrock Floating Offshore Wind Farm Team

Related articles

Principle Power Wins O&M Contract for EFGL Floating Foundations
Operations & Maintenance

Principle Power Wins O&M Contract for EFGL Floating Foundations

24 days ago

Clarksons Wins Port & Agency Services Contract for OranjeWind Offshore Wind Farm
Ports & Logistics

Clarksons Wins Port & Agency Services Contract for OranjeWind Offshore Wind Farm

25 days ago

Daily offshore wind news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free

Related news

Principle Power Wins O&M Contract for EFGL Floating Foundations
Operations & Maintenance

Principle Power Wins O&M Contract for EFGL Floating Foundations

24 days ago
Clarksons Wins Port & Agency Services Contract for OranjeWind Offshore Wind Farm
Ports & Logistics

Clarksons Wins Port & Agency Services Contract for OranjeWind Offshore Wind Farm

25 days ago