The developers of the 3.6 GW Dogger Bank, the world’s largest offshore wind farm, will carry out the first large-scale pilot of a new process that is expected to reduce welding times by as much as 80 per cent.
Ebflow Reduced Pressure Electron Beam (RPEB) welding is expected to be used at the 1.2 GW Dogger Bank A phase of the wind farm, to fabricate welds on offshore wind foundation monopiles, reducing the amount of time it takes to carry out the task from a number of hours to a matter of minutes, the developers said.