Home›Grid Connection›Gwynt Y Mor Readies for Export Cable Corridor Survey Following Cable Issues
Grid Connection

April 14, 2022 · about 4 years ago

Gwynt Y Mor Readies for Export Cable Corridor Survey Following Cable Issues

The Gwynt Y Mor offshore wind farm in the UK is set to undergo a pre-construction survey of its export cable corridor, following a series of export cable issues. Titan Endeavour will carry out the work, starting around 15 April and scheduled to take up to seven days, subject to weather conditions. T

2 minutes read
  • LinkedIn
  • X
  • Email
A photo of the Gwynt y Mor offshore wind farm in the uk

The Gwynt Y Mor offshore wind farm in the UK is set to undergo a pre-construction survey of its export cable corridor, following a series of export cable issues.

Titan Endeavour will carry out the work, starting around 15 April and scheduled to take up to seven days, subject to weather conditions.

The pre-survey of the export cable corridor will be done prior to some maintenance work on one of the export cables being carried out at a later date.

The survey vessel will conduct survey operations on a 12-hour basis.

Gwynt Y Mor, located some 13 kilometers off the coast of North Wales, was put into operation in 2015. That same year the project encountered its first issues with the export cable, which then underwent repair .

Five years later, an operations and maintenance (O&M) contractor performing a routine test of the fibers in the spare fiber optic cable (FOC) discovered that all fibers within the spare FOC within subsea export cable 3 (SSEC3) had failed. This initial FOC break was located close to the location where the repair was undertaken in 2015.

Between February and September 2020, the project’s offshore transmission system owner carried out further tests to check for any degradation of the power cores and to improve the accuracy of the location of the break.

On 15 October 2020, Gwynt y Môr OFTO plc, a consortium comprising Balfour Beatty and Equitix , discovered a second break on the spare FOC within SSEC3, in whose vicinity the main power core of the cable section failed. This second FOC break was located approximately 1.5 kilometers from the initial FOC failure.

Gwynt y Môr OFTO reported the Transmission Services Reduction to Ofgem and filed the Exceptional Event claim, which Ofgem accepted in February 2021.

In May last year, Sumitomo Electric Industries reported that it had won a contract to supply the export cable for the 576 MW offshore wind farm.

Gwynt y Môr features 160 Siemens Gamesa 3.6 MW wind turbines, which can together enough renewable electricity to meet the equivalent needs of approximately 400,000 average UK homes.

The wind farm is owned by RWE, Stadtwerke München, and Macquarie Infrastructure and Real Assets (MIRA).

Follow offshoreWIND.biz on:

Related Articles

Business & Finance

New Export Cable for Gwynt y Môr After Year of Cable Issues

3 min read

Reach the offshoreWIND.biz industry in one go!

offshoreWIND.biz is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow offshoreWIND.biz on:

Filed under

Grid ConnectionOperations & MaintenanceWind Farm Update

Daily offshore wind news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Cadeler Adds Wind Ace to Fleet, First Stop East Anglia Two
  2. 2Turbine Installation at Thor Offshore Wind Farm Reaches Halfway Point
  3. 3South Korean Cable Maker Takes Delivery of Its Second Cable Laying Vessel
  4. 4Aker Solutions Joins Bellrock Floating Offshore Wind Farm Team

Related articles

OWC, KLEM, and OEG Form Korean Offshore Wind Pact
Operations & Maintenance

OWC, KLEM, and OEG Form Korean Offshore Wind Pact

11 days ago

Daily offshore wind news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free

Related news

OWC, KLEM, and OEG Form Korean Offshore Wind Pact
Operations & Maintenance

OWC, KLEM, and OEG Form Korean Offshore Wind Pact

11 days ago