DEME’s vessel Orion has completed the installation of the jacket foundation for Tennet’s Hollandse Kust West Alpha platform in the North Sea off the Dutch coast.
The installation of the 2,300-tonne jacket began last week after the unit arrived at the offshore construction site from the Port of Vlissingen on 14 August, a few weeks after the load out at the Heerema Fabrication Group yard.