All 47 wind turbine jacket foundations and all subsea cables are now in place at the Formosa 2 offshore wind farm in Taiwan. The wind farm also has more than half of its wind turbines installed so far.
The final jacket foundation was installed on 26 August, with the subsea cable works reaching completion on 1 September, said the consortium behind the project, which comprises JERA, Macquarie’s Green Investment Group (Corio Generation), and Swancor Renewable Energy (SRE).