It will supply more than 1.5 million Polish households with renewable energy annually for over 25 years.
The wind farm’s developers PKN Orlen and Northland Power selected Vestas as the preferred supplier. The company will provide 76 of its 236-15.0 MW wind turbines for the project that will be installed by Vestas’ compatriot Cadeler.
In September 2022, the Baltic Power joint venture also announced preferred suppliers of all key onshore and offshore components of the farm: foundations, wind turbines, substations, and cables.
The construction of an onshore substation that will act as a hub for cable lines transmitting electricity from offshore substations located nearly 30 kilometres away is already underway.
Related Article
Baltic Power Onshore Substation Work Kicks Off