For the installation of the monopiles, produced by Sif Group, Van Oord engaged DEME and its jack-up vessel Innovation .
The first of the project’s 69 Siemens Gamesa 11 MW wind turbines was installed in April. Siemens Gamesa and Van Oord are using the offshore installation vessel Scyll a to transport and install the turbines.
Related Article
First Turbine Stands at Hollandse Kust Noord Offshore Wind Farm
The Hollandse Kust Noord wind farm is being developed by CrossWind, a joint venture between Shell and Eneco. The wind farm is expected to supply the first electricity to the Dutch grid by the summer and full commissioning of the project is expected by the end of 2023.