This implies installing more offshore wind capacity at the tendered locations than what was agreed in the climate agreement and other political agreements, and could lead to as much as 14 GW of new generation capacity if implemented at all the tendered areas.
Projects at North Sea I, Kriegers Flak II and Kattegat II have the full green light for overplanting, while at Hesselø and Energy Island Bornholm only a more limited overplanting can be permitted: up to a total capacity of 1.2 GW for Hesselø and up to 3.8 GW for Energy Island Bornholm.