The Aeolus installation vessel started working at the Saint-Brieuc offshore wind farm site in May 2021 and completed the first phase of work at sea on 31 October that year.
The first piling campaign, which was concentrated in the northern zone of the wind farm site to allow for fishing activities in the southern part, faced several setbacks, including malfunctioning drilling equipment , and work being halted by local fishermen.