The 2022 offshore construction campaigns were completed by the end of the year and the works resumed at the beginning of 2023.
Installation of the jacket foundations restarted at the end of June, with 51 jackets in place so far, as well as 35 of the project’s 62 Siemens Gamesa 8 MW wind turbines, which are being installed by Fred. Olsen Windcarrier’s vessel Brave Tern , according to our previous news about the project.