The first eight monopiles for the 2.6 GW Coastal Virginia Offshore Wind (CVOW) project have set sail from EEW SPC’s factory in Rostock, Germany, and are en route to the Portsmouth Marine Terminal in the US.
On 21 September, the first eight monopiles for Dominion Energy’s CVOW project were loaded at the Rostock quayside. In preparation for RoRo loading, the units were lifted into the transport cradle using the Strand Jack system.