The project has been in development since 2012, when the developer received a location decision (so-called permit to erect artificial islands) for project B. In 2013, part C received the location decision.
Ocean Winds signed a grid connection agreement in May 2021. In June last year, the project received the right to a Contract for Difference (CfD) from the Energy Regulatory Office, making it one of the first offshore investments to be completed in Poland.