Furthermore, Van Oord, using its cable-laying vessel Nexus , has also completed the installation of the inter-array cables that started in October.
The company’s remotely-operated trencher Dig-It buried the inter-array cables to the required depth and the termination and testing works on the inter-array cables are now in full swing, and are expected to be completed in the first quarter of 2024.