Sif will be responsible for the manufacturing of the 52 extended monopile foundations that will have no transition pieces, but secondary steel components, and that will have a total weight of approximately 70 kilotonnes.
Transition piece-less monopiles were successfully applied by Sif in earlier projects offshore the Netherlands, including the Hollandse Kust Noord project for Crosswind, another joint venture of Shell and Eneco.