The three-phase 3.6 GW Dogger Bank Wind Farm is being built in UK waters some 130 kilometres off the coast of Yorkshire.
The construction of Dogger Bank A is underway with the project in the wind turbine installation stage and already having produced first power . However, the project is now expected to be put into full operation in 2025 instead of this year , as originally planned, as the challenging weather conditions had impacted wind turbine installation, and vessel availability and supply chain delays further impacted progress, according to SSE’s third-quarter trading update from February.