At the Moray West site, construction work is progressing with the installation of monopiles and transition pieces (TPs) well underway.
Dajin Heavy Industry has also delivered 48 of the project’s 62 monopiles (60 for wind turbines and two for offshore substations), while the remaining 14 have been delivered by Spanish Navantia and Windar . All of the 62 transition pieces for the offshore foundations will be manufactured and delivered by Lamprell.