“The combined technology of the Vibro Hammer and Impact Hammer will also be used on the CVOW project, in combination with state-of-the-art noise mitigation technologies to protect marine mammals,” said Jan Klaassen , Business Unit Director Americas at DEME Offshore.
The monopiles for the 2.6 GW CVOW offshore wind farm are being produced by EEW SPC, which sent off the first batch from its factory in Rostock, Germany, to the Port of Virginia’s Portsmouth Marine Terminal in September 2023. The 176 transition pieces (TPs) will be delivered by Bladt Industries from Denmark.
Related Article
First Coastal Virginia Monopiles En Route to US
The US Department of Interior (DOI) approved the construction and operations plan (COP) for Dominion Energy’s 2.6 GW Coastal Virginia Offshore Wind (CVOW) project in October 2023.
CVOW will comprise 176 Siemens Gamesa 14 MW wind turbines and three offshore substations .
Once fully constructed in 2026, the 2.6 GW offshore wind farm will be able to generate enough electricity to power up to 660,000 households.