Following the installation of the export cables, Boskalis will install a 9-kilometre-long 66 kV interconnector cable between TenneT’s Hollandse Kust West Alpha and Hollandse Kust West Beta offshore substations.
A few days ago, the jacket foundation for the Hollandse Kust (west Beta) and the piles left the Smulders yard in Vlissingen.