Navantia-Windar will be supplying 77 monopile foundations for the project’s turbines and substations, and Steelwind Nordenham will deliver the remaining 34 wind turbine foundations for Baltica 2.
The four 375 MW substations will be designed, manufactured, and commissioned by a consortium of Semco Maritime and PTSC Mechanical & Construction (PTSC M&C) .
PGE and Ørsted plan to complete the construction of Baltica 2 by the end of 2027 and Baltica 3 by the end of the decade. Once fully commissioned, the entire 2.5 GW offshore wind project will provide enough renewable energy to power four million Polish households, according to the developers.