For the execution of the additional scope, Jumbo Offshore provided a project management team and an engineering construction crew. From the contract signature to the completion of the works, the entire project took only five months, including the Fairplayer’s trip from Europe to Taiwan.
The removal work involved the underwater cutting of the monopiles into sections and the recovery, transport and offloading of the sections. The individual sections were lifted into the vessel’s cargo hold for transportation to a local Taiwanese port and offloading to the quayside.