Each foundation measures seven metres in diameter, and lengths vary from 45 metres to 68 metres, to adapt to the different depths of the wind farm’s sitting area.
The 61 foundations will be installed offshore until early 2025, said Ocean Winds. During the works, DEME will leverage its knowledge from the Saint-Nazaire project, utilising similar equipment, including the 350-tonne offshore foundation drill developed with Herrenknecht.