Boskalis’ cable-laying vessel, assisted by the specialized burial sledge tool BSSIII, is poised to repeat the operation of delivering and connecting the second cable to the shore.
Two 65-kilometre-long 220 kV export cables are needed to connect the offshore wind farm to the onshore power grid. About four kilometres offshore, Boskalis’ cable-laying vessel Ndurance will take over the installation of the export cable.