“The Scoping Report is an important milestone for Dogger Bank D and is a key part of the development of an offshore wind farm,” said Rob Cussons , Project Director for Dogger Bank D at SSE Renewables.
“The report lays out the scope of the project proposals and identifies key environmental factors. We look forward to receiving a Scoping Opinion from the Planning Inspectorate and input from consultees which will help inform our development proposals.”
A further round of public consultation on the proposals for Dogger Bank D will take place in Autumn 2024, SSE Renewables said on 28 June.
The filing of the EIA Scoping Report follows the publication of National Grid ESO’s Transitional Centralised Strategic Network Plan (tCSNP2) which included confirmation that Dogger Bank D will connect to Birkhill Wood, a proposed new 400 kV substation located in the East Riding of Yorkshire.
After the confirmation, SSE and Equinor dropped the previous plan to integrate green hydrogen production into Dogger Bank D, focusing entirely on power generation from the proposed offshore wind farm.
Related Article
SSE, Equinor Ditch Green Hydrogen Plans for Dogger Bank D Offshore Wind Farm
If consented and approved for construction, Dogger Bank D would be built some 210 kilometres off the UK’s northeast coast, in the eastern zone of the Dogger Bank C lease area.
The proposed fourth phase of the Dogger Bank Wind Farm has been designated a Nationally Significant Infrastructure Project (NSIP) and is therefore required to apply for a Development Consent Order (DCO) through the NSIP Planning Process. SSE and Equinor said that they were also working closely with The Crown Estate to agree on the progression of the project.
If approved, Dogger Bank D is expected to enter construction in 2029 , at the earliest. Based on this timeline, the construction of the offshore wind farm is anticipated to be completed no later than 2035.
The 2 GW offshore wind farm is planned to comprise a maximum of 122 wind turbines, based on the likely wind turbine models that will be available at the time the project enters construction, which the developers expect to have a rated capacity of between 14 MW and 27+ MW per turbine, according to information in the Scoping Report .
The final selection of wind turbines will be made once further surveys, technical development and engagement with the supply chain have been undertaken with the final decision made post-consent, the developers noted.