Home›Fixed-Bottom›Monopile Installation Continues at Vineyard Wind 1 Site Offshore US
Monopile Installation Continues at Vineyard Wind 1 Site Offshore US

DEME Offshore US is transporting and installing the monopile foundations, TPs, offshore substation, and scour protection, as well as the offshore substation foundation and platform. The company is also responsible for the installation of wind turbines.

The first of 62 monopile foundations, supplied by EEW Special Pipe Constructions (EEW SPC), was installed at the site, 15 miles off the coast of Martha’s Vineyard, in June 2023.

Reach the offshoreWIND.biz industry in one go!

offshoreWIND.biz is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow offshoreWIND.biz on:

Filed under

Fixed-BottomFoundationsProject UpdatesSupply ChainWind Farm Update

Daily offshore wind news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Related articles

OWC, KLEM, and OEG Form Korean Offshore Wind Pact
Operations & Maintenance

OWC, KLEM, and OEG Form Korean Offshore Wind Pact

11 days ago

Principle Power Wins O&M Contract for EFGL Floating Foundations

Daily offshore wind news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free

Related news

OWC, KLEM, and OEG Form Korean Offshore Wind Pact
Operations & Maintenance

OWC, KLEM, and OEG Form Korean Offshore Wind Pact

11 days ago
Principle Power Wins O&M Contract for EFGL Floating Foundations
Operations & Maintenance

Principle Power Wins O&M Contract for EFGL Floating Foundations

12 days ago

The 800 MW offshore wind farm will comprise 62 GE Vernova’s Haliade-X 13 MW wind turbines , each with a 220-metre rotor and 107-metre blades.

Earlier this year, a breakage of the blade on one of the wind turbines occurred, which was caused by a manufacturing deviation, the company’s CEO Scott Strazik revealed during an earnings call in July.

That same month, the US Bureau of Safety and Environmental Enforcement (BSEE) issued an order instructing Vineyard Wind to suspend electricity production from all wind turbines until it could be determined whether the blade failure affected any other of the project’s turbines.

Following authorization in mid-August to resume certain activities, eight new towers and nacelles have been installed on the project, according to Vineyard Wind.

Last week, the company announced that GE Vernova plans to remove some blades and strengthen others as part of their incident and response action plan.

Related Article

GE Vernova Removing More Vineyard Wind Blades While Strengthening Others Following Inspections

Follow offshoreWIND.biz on:

Operations & Maintenance

Principle Power Wins O&M Contract for EFGL Floating Foundations

12 days ago

Fixed-Bottom

October 28, 2024 · about 1 year ago

Monopile Installation Continues at Vineyard Wind 1 Site Offshore US

The DP3 installation vessel Orion, owned and operated by the Belgian offshore construction specialist DEME, is scheduled to begin installing the remaining monopile foundations at the Vineyard Wind 1 site in the US on or around 28 October, as disclosed in the project’s recent offshore wind mariner up

1 minutes read
  • LinkedIn
  • X
  • Email

Trending Now

  1. 1Cadeler Adds Wind Ace to Fleet, First Stop East Anglia Two
  2. 2Turbine Installation at Thor Offshore Wind Farm Reaches Halfway Point
  3. 3South Korean Cable Maker Takes Delivery of Its Second Cable Laying Vessel
  4. 4Aker Solutions Joins Bellrock Floating Offshore Wind Farm Team