Currently, onshore work is underway with the laying of cables at land and the construction of an onshore substation in the municipality of Lemvig.
At the beginning of 2025, seabed preparation for the construction activities will take place and offshore construction will then kick off in spring with the installation of the foundations. Turbine installation is scheduled to begin in 2026 and is planned to be performed from the port of Esbjerg. Thor is expected to be fully operational by no later than the end of 2027, RWE says.