The transition pieces are being installed on the 176 monopiles that are manufactured and delivered by EEW SPC.
In November 2024, Dominion Energy said that 78 monopile foundations and four pin piles for one offshore substation were installed at the CVOW site during the first installation season, with monopile installations set to resume in May 2025 in line with the construction schedule.