Haizea Wind Group and the Navantia-Windar consortium are manufacturing the monopile foundations and transition pieces for the project.
The installation of wind turbine foundations is expected to be completed in the first quarter of 2026.

Haizea Wind Group and the Navantia-Windar consortium are manufacturing the monopile foundations and transition pieces for the project.
The installation of wind turbine foundations is expected to be completed in the first quarter of 2026.
offshoreWIND.biz is read by thousands of professionals every day.
Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.
Follow offshoreWIND.biz on:
Join thousands of industry professionals who start their day with our newsletter.
East Anglia Three will comprise 95 Siemens Gamesa 14+ MW wind turbines , all of which are expected to be operational in 2026.
The 1.4 GW offshore wind farm is the second of ScottishPower Renewables’ East Anglia offshore wind projects to be developed and is part of the East Anglia Hub which includes two other offshore wind farms: the 800 MW East Anglia One North and the 900 MW East Anglia Two .
Follow offshoreWIND.biz on:
10 days ago
about 1 year ago
Seaway7, using the jack-up vessel Seaway Ventus, is scheduled to start installing wind turbine foundations at the East Anglia Three offshore wind farm site at the beginning of April. Seaway Ventus is expected to mobilise at BOW Terminal in the Netherlands on 27 March and commence offshore work withi