Home›Business & Finance›Electrolysis Project Delays May Postpone COD for Lithuania’s First Offshore Wind Farm
Business & Finance

March 19, 2025 · about 1 year ago

Electrolysis Project Delays May Postpone COD for Lithuania’s First Offshore Wind Farm

Ignitis Group, whose company Ignitis Renewables is developing Lithuania’s first offshore wind farm, says the commercial operation date (COD) for the 700 MW project could be postponed as large-scale electrolysis projects across Europe face delays, reducing power offtake visibility. The company, in a

2 minutes read
  • LinkedIn
  • X
  • Email
Electrolysis Project Delays May Postpone COD for Lithuania’s First Offshore Wind Farm

Ignitis, which expects to make a final investment decision (FID) on Curonian Nord after the completion of development and obtaining a construction permit in 2027, revealed that the offshore wind farm’s COD may be delayed in its 2024 results published in February.

“[As] a result of large-scale electrolysis projects being delayed across Europe, including the Baltics, possibilities to secure long-term power offtake have reduced. Combined with challenges in the current offshore wind supply chain environment, financing of the project may become challenging as we approach FID in 2027” , Ignitis states in its 2024 report.

“As a result, there might be a need to delay the project COD until there is more visibility on the electrolysis demand and/or the interconnector with Germany. We will continue to monitor the market developments and will update our plans accordingly.”

In a statement published on 18 March, Ignitis said the development of the 700 MW Curonian Nord project continued and that around EUR 50 million had been invested by the Group to date.

“Of this, EUR 20 million has been paid as a development fee and EUR 30 million has been allocated for environmental impact assessment, wind speed, water and meteorological measurements, various seabed surveys and other necessary works, which for the most part may also be flexibly used in the future without time constraints”, Ignitis said on 18 March.

Last year, Ignitis Renewables prepared an environmental impact assessment (EIA) programme on whose basis the EIA for the project is being conducted, and also started wind and metocean measurement campaigns at the offshore wind farm site.

Related Article

Fugro’s LiDAR Buoy Deployed Offshore Lithuania for 700 MW Wind Project

Ignitis Renewables is also looking to build Lithuania’s second 700 MW offshore wind farm.

In October 2024, the company announced its decision to participate in the Lithuanian Contracts for Difference (CfD) tender and launch a partner selection process for up to 49 per cent ownership in the project.

However, in January 2025, the tender was suspended and is expected to be relaunched this year. Ignitis says it will decide whether to participate in the relaunched tender once the (new) conditions of the tender are known.

Related Article

Lithuania Puts Second Offshore Wind Tender on Hold

Reach the offshoreWIND.biz industry in one go!

offshoreWIND.biz is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow offshoreWIND.biz on:

Filed under

Business & FinanceFixed-BottomProject UpdatesWind Farm Update

Daily offshore wind news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Cadeler Adds Wind Ace to Fleet, First Stop East Anglia Two
  2. 2Turbine Installation at Thor Offshore Wind Farm Reaches Halfway Point
  3. 3South Korean Cable Maker Takes Delivery of Its Second Cable Laying Vessel
  4. 4Aker Solutions Joins Bellrock Floating Offshore Wind Farm Team

Related articles

Aker Solutions Joins Bellrock Floating Offshore Wind Farm Team
Floating Wind

Aker Solutions Joins Bellrock Floating Offshore Wind Farm Team

12 days ago

Principle Power Wins O&M Contract for EFGL Floating Foundations
Operations & Maintenance

Principle Power Wins O&M Contract for EFGL Floating Foundations

13 days ago

Daily offshore wind news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free

Related news

Aker Solutions Joins Bellrock Floating Offshore Wind Farm Team
Floating Wind

Aker Solutions Joins Bellrock Floating Offshore Wind Farm Team

12 days ago
Principle Power Wins O&M Contract for EFGL Floating Foundations
Operations & Maintenance

Principle Power Wins O&M Contract for EFGL Floating Foundations

13 days ago