Vestas is the turbine supplier to CIP’s two existing projects and will also supply 33 units of its latest 15 MW turbine to Fengmiao 1 .
The construction of the offshore wind farm is scheduled to be completed by the end of 2027. Copenhagen Offshore Partners will continue its involvement throughout the construction phase.
A group of six local and international corporations has entered into long-term power purchase agreements with Fengmiao 1 for its entire capacity, with the most recent being MediaTek, a Taiwanese semiconductor company.