The 300 MW TPC Offshore Phase II was one of the eleven offshore wind projects selected by the Taiwanese government in April 2018.
Foxwell Energy, an affiliate of Shinfox, won the tender from Taipower for the development of the wind farm at a total contract cost of TWD 62.88 billion (EUR 2.02 billion) in June 2020.
Located approximately 14.7 kilometres west of Lukang in Changhua County, the project is expected to generate 1 GWh of power per year and could generate enough renewable electricity to supply approximately 270,000 households.