Seaway7 secured a contract for Dogger Bank A and B in the summer of 2020, and the following year, the company was awarded another one for the same work on Dogger Bank C.
The monopiles and transition pieces (TPs) are manufactured by Sif and Smulders, who are the suppliers for all three phases of the 3.6 GW project.
The first two 1.2 GW phases, Dogger Bank A and Dogger Bank B, will each comprise 95 Haliade-X 13 MW turbines. The third phase, Dogger Bank C, will feature 87 Haliade-X 14 MW turbines.
Dogger Bank Wind Farm is owned by SSE Renewables (40 per cent), Equinor (40 per cent), and Vårgrønn (20 per cent).