The 660 MW Nordseecluster A will comprise 45 monopile foundations, of which 44 will carry the Vestas V236-15.0 MW wind turbines and one to support the project’s offshore substation.
The first monopiles, manufactured by Dajin Heavy Industry, have already arrived at the Buss Terminal in the port of Eemshaven, the Netherlands.
Nordseecluster A is expected to be fully connected to the grid in 2027.
The second phase, Nordseecluster B, will add a further 900 MW of capacity, with commercial operation expected to begin in early 2029.