In March this year, the offshore substation for Hai Long 3 was installed, followed by the first wind turbine installation and onshore substation energisation test in April. Last month, the energisation tests for subsea cables and the Hai Long 2 offshore substation, installed in May 2024, were completed, enabling grid connection.
This month, CSBC-DEME Wind Engineering (CDWE) , using its heavy lift vessel Green Jade, finished the installation of all 219 pin piles at the Hai Long sites, located approximately 45-70 kilometres off the Changhua coast in the Taiwan Strait.
Related Article
All Pin Piles In at Hai Long Offshore Wind Farm, Next Up Hai Long 3 Jacket Foundations
With a planned capacity of 1 GW, Hai Long is said to play a vital role in supporting Taiwan’s renewable energy target of 15 GW of offshore wind between 2026 and 2035.
Once operational, the project will be among the largest offshore wind farms in the Asia Pacific region, providing renewable energy to over one million Taiwanese homes.
Follow offshoreWIND.biz on: