From 2026, two platform topsides will be built at the production site for the LanWin2 and BalWin3 grid connection systems, which are scheduled to transmit offshore wind power from the German North Sea to land in 2030 and 2031, respectively.
The onshore and offshore export cable systems for LanWin2 will be delivered by Nexans under a contract signed with TenneT in January 2025.