Share this article
The Town and County of Nantucket in Massachusetts and GE Vernova have reached a settlement agreement worth USD 10.5 million (approximately EUR 9 million), which the wind turbine OEM will pay to compensate the Town and local businesses for losses resulting from the failure of a turbine blade on the Vineyard Wind 1 offshore wind project in the summer of 2024.
On 13 July 2024, a blade damage incident took place on one of the turbines installed on Vineyard Wind 1, located 15 miles (approximately 24 kilometres) off the coast of Massachusetts. Following an investigation, GE Vernova found that the damage was a result of a manufacturing deviation , and later decided to remove the blades that were produced in the same factory.
A few days after the incident, the company said that a “significant part” of the remaining blade came loose from the turbine and mobilised debris recovery teams.
On 16 July last year, GE Vernova said it had recovered three large fragments as it continued to monitor the offshore area for any floating blade debris, which consists of non-toxic fibreglass fragments ranging in size from small pieces to large sections.
Related Article
Vineyard Wind Commences Debris Recovery Following Turbine Blade Incident
The Town of Nantucket said on 11 July 2025, as it reached a definitive settlement agreement with GE Vernova, that the incident scattered foam, fibreglass, and other debris along Nantucket’s shores during the height of the summer tourist season.
“When the blade failed, debris settled on the ocean floor, entered the water table, and littered Nantucket’s beaches for months, requiring an extensive cleanup effort in which many community members joined” , the Town of Nantucket said in a press release on 11 July.