Share this article
Taihan Cable & Solution has completed the installation of export cables for the 364.8 MW Yeonggwang Nakwol offshore wind project in South Korea.
The export cable installation, covering two 28-kilometre lines and carried out by Taihan’s cable-laying vessel (CLV) PALOS , was performed in two phases. The first phase took place over two weeks in mid-May, and the second phase began in late June and was completed last week, according to the company.
The installation of the inter-array cables, also produced by Taihan, is scheduled to commence after July.
Developed by Nakwol Blue Heart, the Yeonggwang Nakwol offshore wind project is located near Songido, Nakwol-myeon, Yeonggwang-gun, Jeollanam-do, off the coast of South Korea.
With a total project cost of KRW 2.3 trillion (approximately EUR 1.42 billion) and a capacity of 364.8 MW, the wind farm is expected to generate enough electricity to power about 250,000 households year-round upon completion. The overall project progress has now surpassed 50 per cent, said Taihan.
Related Article
Thai Conglomerate Invests in 740 MW Wind Projects Offshore South Korea
PALOS , introduced in November 2023, is a specialised cable-laying vessel acquired to secure Taihan’s turnkey competitiveness, spanning production, transportation, installation, and maintenance of submarine cables.
As Korea’s only CLV, it was purpose-built from the design stage for submarine cable installation.
The vessel is a hybrid model capable of operating in both Dynamic Positioning Class 2 (DP2) mode and Anchoring mode. It also features a flat-bottom design that allows independent access to very shallow coastal areas, enabling all-weather deployment across diverse marine environments.
