Spain’s Haizea Wind Group has rolled out the first monopile for Ørsted’s 2.9 GW Hornsea 3 offshore wind farm in the UK.
The monopile will now undergo its surface treatment before being shipped to the offshore wind farm project, located approximately 120 kilometres off the Norfolk Coast in the North Sea.
In September 2022, Haizea Wind Group signed a contract for the supply of the XXL monopiles that will be delivered in the port of Bilbao .
Related Article
Haizea to Deliver XXL Monopiles for Hornsea Three
The monopiles will be installed at the project’s site by Cadeler under a contract signed with Ørsted in April 2023.
Recently, Acteon, through its marine foundations business line, MENCK, secured a contract to supply pile-driving equipment and operational services for the monopile installation of Hornsea 3.
The UK-headquartered company will supply its MENCK MHU4400S hydraulic hammer, along with a pile sleeve and an anvil, designed for monopiles of up to eleven metres in diameter.
Related Article
Acteon to Supply Hydraulic Hammer for Hornsea 3 Monopile Installation
The monopiles will be stored at Steel River Quay on the Teesworks site before they are loaded onto offshore wind installation vessels.
The Hornsea 3 offshore wind project will comprise around 200 Siemens Gamesa’s 14 MW wind turbines and is expected to be operational in 2027.