Skyborn Renewables has signed preferred supplier agreements (PSAs) for monopiles, transition pieces, foundation installation and inter-array cable supply and installation for the 976.5 MW Gennaker offshore wind project in the German Baltic Sea.
EEW Special Pipe Construction (EEW SPC) has been selected for the supply of 63 monopiles, which the company will manufacture in Rostock, only 40 kilometres from the Gennaker site. The 63 accompanying transition pieces will be delivered by Dajin Heavy Industry and manufactured in Penglai, China, with final work to be performed in Odense, Denmark.
Skyborn has also signed a PSA with Seaway7 for the transportation and installation of monopiles and transition pieces for the project.
A consortium of Boskalis and TKF has been selected for the supply and installation of approximately 140 kilometres of inter-array cables, which will be manufactured in Eemshaven, Netherlands.
These PSAs come shortly after Skyborn confirmed the execution of the wind turbine supply and long-term service agreements with Siemens Gamesa for its SG 14-236 turbines.
Related Article
Siemens Gamesa Secures Conditional Turbine Order for Skyborn’s German Offshore Wind Farm
Skyborn also entered a PSA with Fred. Olsen Windcarrier for the offshore transportation and installation of the wind turbines, with the charter party agreement expected to be signed later in 2025.
Offshore installation of the 63 wind turbines is planned to commence in 2028 and will be carried out by Fred. Olsen Windcarrier’s Brave Tern jack-up vessel.