DEME has secured a contract for the transport and installation of inter-array cables on the 900 MW Nordseecluster B offshore wind farm in the German North Sea, owned by RWE (51 per cent) and Norges Bank Investment Management (49 per cent).
Under the contract, the Belgian offshore construction specialist will transport and install a total of 124 kilometres of inter-array cables that will connect all 60 wind turbine foundations to the project’s offshore substation. The scope of work for DEME includes all the engineering, preparation and supporting activities.
The work will start towards the end of 2027, when DEME will deploy its cable installation vessel Living Stone , as well as additional supporting equipment.
The company said on 2 October that this was a “sizable” contract, which at DEME means a contract value between EUR 50 million and EUR 150 million.
Nordseecluster B is the second phase of the 1.6 GW Nordseecluster project in Germany, located some 50 kilometres north of the island of Juist.
The first phase, the 660 MW Nordseecluster A, is already under construction with foundation installation underway.
Related Article
First Monopile Stands at 660 MW Nordseecluster A Offshore Wind Farm in Germany
Both phases will feature Vestas 15 MW wind turbines.
Installation of 44 Vestas V236-15.0 MW wind turbines on the first phase is expected to start in 2026, with Nordseecluster A beginning commercial operation in early 2027.