Ørsted has completed the 2025 foundation installation campaign at the Sunrise Wind offshore project site in the US and is now commencing cable installation works on both its projects under construction in the Northeast US, Revolution Wind and Sunrise Wind.
According to the latest Notice to Mariners from the developer, Bokalift 2 and Bokalift 1 have concluded foundation installation for the 2025 season, which was underway at Sunrise Wind, while the wind turbine installation vessel (WTIV) Scylla continues work at the Revolution Wind site.
Related Article
First Monopiles In at New US Offshore Wind Farm, Saipem 7000 En Route to Install OSS
Offshore substations are in place at both offshore wind farm sites and are now undergoing commissioning.
Currently, the vessel Hydra is stationed within the Revolution Wind area for offshore substation commissioning, while Leviathan is deployed for the same work on Sunrise Wind, where the substation was recently installed.
Related Article
Substation Installed at Ørsted’s New US Offshore Wind Farm
Seaway Aimery has begun seabed preparation and cable installation for Revolution Wind’s 2025 inter-array and inter-link cable campaigns, with the vessel Volantis deployed for cable trenching.
At the Sunrise Wind site, export cable work has begun. Northstar Commander is conducting seabed preparation beginning along the nearshore section of the export cable. Soon, a lift boat will also arrive at the HDD exit pit to prepare for the export cable pull-in.