The US District Court for the District of Columbia has granted the preliminary injunction sought by the joint venture between Ørsted and Skyborn Renewables for the Revolution Wind project, which was ordered to pause construction by the US government. When the stop-work order was issued on 22 December 2025, the 704 MW project had seven wind turbines left to install.
The underlying lawsuit that the Revolution Wind joint venture filed against the first stop-work order issued for the offshore wind farm on 22 August 2025, which was supplemented to also challenge the 22 December 2025 order, continues to progress in the court, while the preliminary injunction will allow the construction activities to restart immediately.
“The Project will resume construction work as soon as possible, with safety as the top priority, and to deliver affordable, reliable power to the Northeast”, Ørsted said on 12 January.
On 1 January 2026, when the joint venture lodged the supplemental complaint and announced it would seek a preliminary injunction, Ørsted said that 704 MW Revolution Wind was approximately 87 per cent complete and was expected to begin generating power this month.
Related Article
Ørsted-Skyborn JV Takes Legal Action Against US Gov’t Over Stop-Work Order; Seven Turbines Left to Install on Revolution Wind
After the US federal court granted the preliminary injunction, the US offshore renewable energy industry organisation, Oceantic Network, said that Revolution Wind sparked investments in Louisiana and New England shipyards, purchased export cables from a South Carolina factory, and spurred a steel supply chain that crosses New York and created hundreds of union jobs in Providence, Rhode Island.